This is the foundation of Korea Surface Treatment Co., Ltd. (KST) that elevates perfection.
Facility Overview
We are equipped with various auxiliary facilities to meet the production requirements of the chemical line (temperature, solution concentration, water quality, etc.) and the painting line (temperature/humidity, drying temperature, etc.),
as well as to comply with environmental regulations related to air and water quality.
These facilities contribute to ensuring process stability and product quality.
Major Facilities
Specification
- Boiler 5ton X 2 units
- Air Compressor 50HP X 2 units
- Chiller 650RT/80RT
- Air Handling Unit (AHU) 3 units (1350/936/550CMM) and Gas Burner
Remarks
- Low-NOx Condensing Boiler
- Oil-Free Air Compressor
- COP 6.0 2-Stage Turbo
Specification
- Chemical Scrubber (3 units)
- Painting A/C Tower (4 units), TOPCOAT A/C Tower (1 unit)
Remarks
- 1450CMM X 2 units, FPI Line 960CMM X 1 unit
- Booth 1350/936CMM, Oven 80/80CMM, Booth 550/Oven 50CMM
Specification
- RO (Reverse Osmosis) system producing 10 tons per hour
(Raw water/DI storage tank 50ton)
Remarks
- Can replace 13 water tanks 31 times a month at full operation
- pH 5.5~7.0, SiO₂ 1.0ppm, Electrical Conductivity 10㎲/cm
Specification
- Wastewater collection tank total 400ton
- Undiluted solution (acid/alkali) temporary collection tank 200ton
- Wastewater treatment capacity 12.5ton/hour
Remarks
- The discharged wastewater is transferred to the wastewater terminal treatment plant of Sacheon 1st Industrial Complex
via the wastewater relay pump station within the complex.